Which of the following is not an example of programmable automation?


A) N/C machines
B) Robots
C) Computer-integrated manufacturing
D) Flexible manufacturing systems
E) I Manual automation

F) C) and D)
G) B) and D)

Correct Answer

verifed

verified

A production line is to be designed for a job with three tasks.The task times are 0.5 minutes,1.8 minutes,and 1.1 minutes.If the necessary cycle time is 1.0 minutes per unit,what is the actual minimum number of workstations possible?


A) 1
B) 2
C) 3
D) 4
E) 5

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

Repetitive process systems are typically used to produce goods for specific customer orders rather than goods to be held as finished product inventory in anticipation of demand.

A) True
B) False

Correct Answer

verifed

verified

A precedence network matrix shows the combination of a product's quantity and variety,and the flexibility of the processes that make it.

A) True
B) False

Correct Answer

verifed

verified

A company needs to locate three departments (X,Y,and Z) in the three areas (I,II,and III) of a new facility.They want to minimize interdepartmental transportation costs,which are expected to be $.50 per load per metre moved.An analyst has prepared the following distances and flow matrices: A company needs to locate three departments (X,Y,and Z) in the three areas (I,II,and III) of a new facility.They want to minimize interdepartmental transportation costs,which are expected to be $.50 per load per metre moved.An analyst has prepared the following distances and flow matrices:   What is the total flow (loads per week) between department Y and department Z? A) 140 B) 160 C) 200 D) 250 E) 300 What is the total flow (loads per week) between department Y and department Z?


A) 140
B) 160
C) 200
D) 250
E) 300

F) A) and D)
G) C) and D)

Correct Answer

verifed

verified

The type of layout which is used to achieve a smooth and rapid flow of large volumes of standardized goods or services is:


A) process.
B) product.
C) intermittent.
D) cellular.
E) continuous.

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

The design of factories and the design of warehouses are based on a similar set of factors.

A) True
B) False

Correct Answer

verifed

verified

A common goal in designing process layouts is:


A) minimizing the number of workers.
B) minimizing idle time.
C) minimizing transportation costs.
D) maximizing work-station productive time.
E) maximizing transportation distances.

F) A) and D)
G) A) and B)

Correct Answer

verifed

verified

Process design determines the structure of a process-that is,the sequence of operations (the workflow),resources,and controls needed for a particular process.

A) True
B) False

Correct Answer

verifed

verified

Process design determines the structure of a process-that is,the sequence of operations (the workflow),resources,and controls needed for a particular process

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not true about design of process layouts?


A) Design Process layouts are influenced by physical factors such as location of entrances.
B) Ideally the physical structure is designed around the process layout.
C) There is a standardized approach to develop process layouts.
D) The main issue in design of process layouts is the relative positioning of departments.
E) Multilevel structures pose special problems for process layout planners.

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

Given the following line balance data: Given the following line balance data:    What is the maximum sensible cycle time? What is the maximum sensible cycle time?

Correct Answer

verifed

verified

A company needs to locate three departments (X,Y,and Z) in the three areas (1,2,and 3) of a new facility.They want to minimize interdepartmental transportation costs,which are expected to be $.50 per load metre moved.An analyst has prepared the following flow and distance matrices: A company needs to locate three departments (X,Y,and Z) in the three areas (1,2,and 3) of a new facility.They want to minimize interdepartmental transportation costs,which are expected to be $.50 per load metre moved.An analyst has prepared the following flow and distance matrices:   If the company were to locate departments X,Y,and Z in areas 1,2,and 3,respectively,what would be the total distance (in metres) loads would be moved each week? A) 3,100 B) 3,600 C) 6,200 D) 6,700 E) 8,200 If the company were to locate departments X,Y,and Z in areas 1,2,and 3,respectively,what would be the total distance (in metres) loads would be moved each week?


A) 3,100
B) 3,600
C) 6,200
D) 6,700
E) 8,200

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

A company needs to locate three departments (X,Y,and Z) in the three areas (1,2,and 3) of a new facility.They want to minimize interdepartmental transportation costs,which are expected to be $.50 per load metre moved.An analyst has prepared the following flow and distance matrices: A company needs to locate three departments (X,Y,and Z) in the three areas (1,2,and 3) of a new facility.They want to minimize interdepartmental transportation costs,which are expected to be $.50 per load metre moved.An analyst has prepared the following flow and distance matrices:   What is the distance (in metres) from area 3 to area 1 of this new facility? A) 0 B) 10 C) 20 D) 30 E) 40 What is the distance (in metres) from area 3 to area 1 of this new facility?


A) 0
B) 10
C) 20
D) 30
E) 40

F) A) and C)
G) A) and D)

Correct Answer

verifed

verified

Process layouts tend to have lower in-process inventories,and higher equipment utilization rates than product layouts.

A) True
B) False

Correct Answer

verifed

verified

A swim lane diagram is a process map used for which type of process?


A) Job shop
B) Process (product) layout
C) Process (functional) layout
D) Cellular layout
E) Processes with interaction

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

"Balance delay" is another name for the percentage of idle time in a product layout.

A) True
B) False

Correct Answer

verifed

verified

The type of layout which arranges production resources according to similarity of function is:


A) process.
B) product.
C) intermittent.
D) cellular.
E) continuous.

F) C) and D)
G) None of the above

Correct Answer

verifed

verified

A consultant needs to locate four departments-waiting room (W) ,checkup room (c) ,laboratory (L) ,and exercise room (E) -in four areas (I,II,III,IV) of a new facility.He wants to minimize interdepartmental transportation costs associated with the nurses escorting patients,which he expects to be $.10 per patient per metre.He has prepared the following distance and flow matrices: A consultant needs to locate four departments-waiting room (W) ,checkup room (c) ,laboratory (L) ,and exercise room (E) -in four areas (I,II,III,IV) of a new facility.He wants to minimize interdepartmental transportation costs associated with the nurses escorting patients,which he expects to be $.10 per patient per metre.He has prepared the following distance and flow matrices:   How many different process layouts are possible for this new facility? A) 4 B) 6 C) 16 D) 24 E) 120 How many different process layouts are possible for this new facility?


A) 4
B) 6
C) 16
D) 24
E) 120

F) B) and E)
G) B) and D)

Correct Answer

verifed

verified

A disadvantage of automation is that it tends to increase variable costs for repetitive operational tasks.

A) True
B) False

Correct Answer

verifed

verified