Job X arrived at work center Q at noon.At 2 p.m.that same day X was begun.X left work center Q at 3:15 p.m.that same day.X's flow time, in minutes, was __________.


A) 195
B) 120
C) 75
D) 60
E) Cannot be determined

F) B) and D)
G) B) and E)

Correct Answer

verifed

verified

Priority rules are widely used to sequence jobs in high-volume systems.

A) True
B) False

Correct Answer

verifed

verified

Bottlenecks may shift with the passage of time, so that different operations become bottleneck operations at different times.

A) True
B) False

Correct Answer

verifed

verified

The matrix below shows relative costs for various job-machine combinations.Which set of pairs constitutes the minimum-cost solution using the Assignment method? The matrix below shows relative costs for various job-machine combinations.Which set of pairs constitutes the minimum-cost solution using the Assignment method?   A) 1-B, 2-C, 3-A B) 1-B, 2-A, 3-C C) 1-A, 2-C, 3-B D) 1-A, 2-B, 3-C E) 1-C, 2-A, 3-B


A) 1-B, 2-C, 3-A
B) 1-B, 2-A, 3-C
C) 1-A, 2-C, 3-B
D) 1-A, 2-B, 3-C
E) 1-C, 2-A, 3-B

F) D) and E)
G) C) and E)

Correct Answer

verifed

verified

For the optimal schedule, what is the total number of hours required to complete these jobs?


A) 23 hours
B) 22 hours
C) 21 hours
D) 20 hours
E) 19 hours

F) B) and E)
G) A) and D)

Correct Answer

verifed

verified

In an assignment model where there are fewer jobs than resources:


A) Dummy jobs are needed to solve the problem.
B) Dummy resources are needed to solve the problem.
C) The problem can't be solved using an assignment model.
D) The problem will have multiple optimum solutions.
E) The simplex method must be used to solve the problem.

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

What is the sequence which will minimize throughput time?

Correct Answer

verifed

verified

Where in the optimum sequence should car E be scheduled?


A) first
B) second
C) third
D) fourth
E) fifth

F) C) and E)
G) D) and E)

Correct Answer

verifed

verified

Can an optimum assignment be made after the row and column reductions?

Correct Answer

verifed

verified

A manager must assign four engineers to projects, one to a project.The leader of Project C has indicated that he does not want engineer 2 or 3 on his project.Given the cost figures below for each project-engineer combination, and keeping in mind that two combinations are undesirable, determine assignments such that total cost will be minimized.

Correct Answer

verifed

verified

Can an optimum assignment be made after the first modification of the row and column reductions table?

Correct Answer

verifed

verified

The SPT rule minimizes idle time for subsequent operations.

A) True
B) False

Correct Answer

verifed

verified

What is the idle time at machine B for the optimum schedule?

Correct Answer

verifed

verified

In an assignment method problem, if it takes Abe 3 hours to build a birdhouse and 4 hours for a doghouse, while Betty takes 4 hours for a birdhouse and 3 hours for a doghouse, what is the reduced cost (in hours) of assigning Abe to build the doghouse?


A) 0 hours
B) 1 hour
C) 2 hours
D) 3 hours
E) 4 hours

F) B) and C)
G) All of the above

Correct Answer

verifed

verified

What is the optimum job sequence for the jobs listed below using Johnson's Rule? What is the optimum job sequence for the jobs listed below using Johnson's Rule?   A) e-g-f-d B) d-g-f-e C) d-f-g-e D) e-d-f-g E) f-e-d-g


A) e-g-f-d
B) d-g-f-e
C) d-f-g-e
D) e-d-f-g
E) f-e-d-g

F) B) and D)
G) B) and E)

Correct Answer

verifed

verified

The purpose of cyclical scheduling is to:


A) eliminate weekends and holidays
B) rotate schedules
C) add flexible hours
D) incorporate overtime
E) observe work patterns

F) All of the above
G) A) and D)

Correct Answer

verifed

verified

If he uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average number of jobs in his shop today?


A) 0
B) 1
C) 2
D) 3
E) 4

F) A) and C)
G) A) and B)

Correct Answer

verifed

verified

What is the average completion time for the shortest processing time (SPT) priority rule? Average job tardiness? Average number of jobs at the center?

Correct Answer

verifed

verified

10 days; 4...

View Answer

Using the cost information given in the table below, assign work crews to jobs so that total cost is minimized.

Correct Answer

verifed

verified

In a single work center, makespan improvement can be accomplished by selecting the optimal sequencing rule.

A) True
B) False

Correct Answer

verifed

verified

Showing 101 - 120 of 134