Filters
Question type

Study Flashcards

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B  A  C, D 445056 B  D 456075 C  E 424548 D  F 314049 E  F 273639 F  End 587082\begin{array}{l}\begin{array} { l c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B } & - & - & - \\\text { A } & \text { C, D } & 44 & 50 & 56 \\\text { B } & \text { D } & 45 & 60 & 75 \\\text { C } & \text { E } & 42 & 45 & 48 \\\text { D } & \text { F } & 31 & 40 & 49 \\\text { E } & \text { F } & 27 & 36 & 39 \\\text { F } & \text { End } & 58 & 70 & 82\end{array}\end{array} What is the estimated slack time for activity D?


A) 0 days
B) 30 days
C) 40 days
D) 50 days
E) 100 days

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

Which of the following leads to simulation being a useful tool with uncertain activity times?


A) paths that are not independent
B) activity times that are not deterministic
C) activity times that cannot be crashed
D) noncritical paths that have no variability
E) critical paths with activities with deterministic time estimates

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

The advantage a precedence diagram has over a Gantt chart is:


A) its ability to reveal relationships among activities.
B) its difficulty in depicting networks.
C) its complexity.
D) its simplicity.
E) its lack of riskiness.

F) A) and B)
G) A) and E)

Correct Answer

verifed

verified

Which of the following is not one of the six key decisions in project management? (I) Selecting the project team (II) Deciding on the project manager's title (III) Managing and controlling project resources (IV) Deciding which projects to implement (V) Selecting the project manager


A) I
B) II
C) III
D) IV
E) V

F) C) and D)
G) D) and E)

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Activity  Precedes  Normal  Time (wks)  Crashing  Cost (1st  week) (2nd  week)  Start  A, B  A  C, D 68 B  G 456 C  E 4 D  F 566 E  H 688 F  H 6710 G  I 835 H  End 51215 I  End 65\begin{array} { l c c c c } \text { Activity } & \text { Precedes } & \begin{array} { c } \text { Normal } \\\text { Time (wks) }\end{array} & \begin{array} { c } \text { Crashing } \\\text { Cost } \left( 1 ^ { \text {st } } \right. \text { week) }\end{array} & \left( 2 ^ { \text {nd } } \right. \text { week) } \\\hline\text { Start } & \text { A, B } & - & - & - \\\text { A } & \text { C, D } & 6 & 8 & - \\\text { B } & \text { G } & 4 & 5 & 6 \\\text { C } & \text { E } & 4 & - & - \\\text { D } & \text { F } & 5 & 6 & 6 \\\text { E } & \text { H } & 6 & 8 & 8 \\\text { F } & \text { H } & 6 & 7 & 10 \\\text { G } & \text { I } & 8 & 3 & 5 \\\text { H } & \text { End } & 5 & 12 & 15 \\\text { I } & \text { End } & 6 & 5 & -\end{array} What is the total cost of reducing this project by two weeks?

Correct Answer

verifed

verified

Total cost...

View Answer

Once a project is approved and underway, project managers are only responsible for effectively managing time and costs which, if done well, will assure project completion on time and on budget.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Time Estimates (wks)   Start  Finish  Activity  Node  Node t0tmtp A 12112029 B 23258 C 24183042 D 3471013 E 14314043\begin{array}{r}{\text { Time Estimates (wks) }} \\\begin{array}{lccccc}& \text { Start } & \text { Finish } \\\text { Activity } & \text { Node } \quad\quad& \text { Node } \quad\quad& \mathrm{t}_{0} \quad\quad& \mathrm{t}_{\mathrm{m}} \quad& \mathrm{t}_{\mathrm{p}} \quad\\\hline \text { A } & 1 & 2 & 11 & 20 & 29 \\\text { B } & 2 & 3 & 2 & 5 & 8 \\\text { C } & 2 & 4 & 18 & 30 & 42 \\\text { D } & 3 & 4 & 7 & 10 & 13 \\\text { E } & 1 & 4 & 31 & 40 & 43\end{array}\end{array} What is the estimated standard deviation in the time for activity E?


A) 0 weeks
B) 1 week
C) 2 weeks
D) 3 weeks
E) 4 weeks

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

The probability of occurrence of risk events is lower near the beginning of a project and higher near the end of the project since very few activities remain.

A) True
B) False

Correct Answer

verifed

verified

In order to determine the probability of timely project completion, it is sometimes necessary to take into account paths other than the critical path.

A) True
B) False

Correct Answer

verifed

verified

Activities not on the critical path have a slack time equal to zero.

A) True
B) False

Correct Answer

verifed

verified

Consider the portion of a project depicted by this graph: Consider the portion of a project depicted by this graph:   What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23? A)  18 B)  17 C)  13 D)  12 E)  10 What is the latest start time of activity 6-7 if the latest finish of activity 7-8 is 26, and the latest finish of activity 7-9 is 23?


A) 18
B) 17
C) 13
D) 12
E) 10

F) None of the above
G) D) and E)

Correct Answer

verifed

verified

Which of the following stages is that one in which the project's expected costs, benefits, and risks are assessed?


A) executing
B) monitoring/controlling
C) assessment
D) planning
E) initiating

F) None of the above
G) A) and E)

Correct Answer

verifed

verified

Matrix organizations transfer control of workers to project managers for the duration of the project.

A) True
B) False

Correct Answer

verifed

verified

The total cost of crashing any one activity should never exceed 20 percent of the total cost of the original project.

A) True
B) False

Correct Answer

verifed

verified

The project management strategy of injecting additional resources in order to reduce the length of the project is called:


A) expediting.
B) rushing.
C) panicking.
D) crashing.
E) loading.

F) None of the above
G) C) and D)

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B  A  C, D 445056 B  D 456075 C  E 424548 D  F 314049 E  F 273639 F  End 587082\begin{array}{l}\begin{array} { l c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B } & - & - & - \\\text { A } & \text { C, D } & 44 & 50 & 56 \\\text { B } & \text { D } & 45 & 60 & 75 \\\text { C } & \text { E } & 42 & 45 & 48 \\\text { D } & \text { F } & 31 & 40 & 49 \\\text { E } & \text { F } & 27 & 36 & 39 \\\text { F } & \text { End } & 58 & 70 & 82\end{array}\end{array} What is the probability that the critical path for this project will be completed within 210 days?


A) 0.5000
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

In the execution phase of a project's life cycle, activities are guided by decisions that were made in the __________ phase.


A) initiating
B) planning
C) monitoring/controlling
D) closing
E) assessment

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Duration Estimate (Days)  Start  Finish  Activity  Node  Node  Optimistic  Most Likely  Pessimistic  A 1291521 B 13132123 C 246918 D 25233547 E 35192627 F 46232941 G 56142026 H 67258\begin{array}{r} \text { Duration Estimate (Days) }\quad \quad \quad \quad \\\begin{array}{lccccc} & \text { Start } & \text { Finish } \\\text { Activity } & \text { Node } & \text { Node } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { A } & 1 & 2 & 9 & 15 & 21 \\\text { B } & 1 & 3 & 13 & 21 & 23 \\\text { C } & 2 & 4 & 6 & 9 & 18 \\\text { D } & 2 & 5 & 23 & 35 & 47 \\\text { E } & 3 & 5 & 19 & 26 & 27 \\\text { F } & 4 & 6 & 23 & 29 & 41 \\\text { G } & 5 & 6 & 14 & 20 & 26 \\\text { H } & 6 & 7 & 2 & 5 & 8\end{array}\end{array} What are the estimated standard deviations (in weeks) in the times for activities A-H?

Correct Answer

verifed

verified

2; 1.67; 2...

View Answer

There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2 days. The standard deviation of the critical path is:


A) 3.
B) 5.
C) 9.
D) 16.
E) 25.

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B, C  A  D 385062 B  E 9099108 C  End 85100115 D  F 192531 E  End 91100115 F  End 626568\begin{array}{l}\begin{array} { c c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B, C } & - & - & - \\\text { A } & \text { D } & 38 & 50 & 62 \\\text { B } & \text { E } & 90 & 99 & 108 \\\text { C } & \text { End } & 85 & 100 & 115 \\\text { D } & \text { F } & 19 & 25 & 31 \\\text { E } & \text { End } & 91 & 100 & 115 \\\text { F } & \text { End } & 62 & 65 & 68\end{array}\end{array} What is the estimated expected (mean) time for activity E?


A) 91 days
B) 99 days
C) 100 days
D) 101 days
E) 115 days

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

Showing 41 - 60 of 137

Related Exams

Show Answer