Filters
Question type

Study Flashcards

If a line is balanced with 80 percent efficiency, the "balance delay" will be:


A) 20 percent.
B) 80 percent.
C) 100 percent.
D) unknown, since balance delay is not related to efficiency.
E) depends on the next operation.

F) None of the above
G) C) and D)

Correct Answer

verifed

verified

Which of the following is not true about process layouts when they are compared to product layouts?


A) higher in-process inventories
B) lower span of supervision
C) lower rates of output
D) more involved cost accounting
E) lower unit costs

F) B) and E)
G) B) and D)

Correct Answer

verifed

verified

Given the following line balance data:  Task  Predecessor  Time (seconds) t none 15ut14vt7wu6xv8yw,x10zy21\begin{array} { l c c } \text { Task } & \text { Predecessor } & \text { Time (seconds) } \\\hline \mathrm { t } & \text { none } & 15 \\\mathrm { u } & \mathrm { t } & 14 \\\mathrm { v } & \mathrm { t } & 7 \\\mathrm { w } & \mathrm { u } & 6 \\\mathrm { x } & \mathrm { v } & 8 \\\mathrm { y } & \mathrm { w } , \mathrm { x } & 10 \\\mathrm { z } & \mathrm { y } & 21\end{array} What is the maximum possible cycle time?

Correct Answer

verifed

verified

A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:  Task  Time (secs)   Immediate Predecessor u30 none v30uw6ux12wy54xz30v,y\begin{array} { l l l } \text { Task } & \text { Time (secs) } & \text { Immediate Predecessor } \\\hline \mathrm { u } & 30 & \text { none } \\\mathrm { v } & 30 & \mathrm { u } \\\mathrm { w } & 6 & \mathrm { u } \\\mathrm { x } & 12 & \mathrm { w } \\\mathrm { y } & 54 & \mathrm { x } \\\mathrm { z } & 30 & \mathrm { v } , \mathrm { y }\end{array} If the company wants the output rate to be equal to demand, what is the minimum number of workstations needed?


A) 3
B) 4
C) 5
D) 6
E) 7

F) B) and D)
G) B) and E)

Correct Answer

verifed

verified

A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:  Task  Time (secs)   Immediate Predecessor u30 none v30uw6ux12wy54xz30v,y\begin{array} { l l l } \text { Task } & \text { Time (secs) } & \text { Immediate Predecessor } \\\hline \mathrm { u } & 30 & \text { none } \\\mathrm { v } & 30 & \mathrm { u } \\\mathrm { w } & 6 & \mathrm { u } \\\mathrm { x } & 12 & \mathrm { w } \\\mathrm { y } & 54 & \mathrm { x } \\\mathrm { z } & 30 & \mathrm { v } , \mathrm { y }\end{array} If the company wants the output rate to be equal to demand, what is the desired cycle time (in seconds) ?


A) 162
B) 72
C) 54
D) 12
E) 60

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Which of the following is not a process commonly considered in making products or delivering services?


A) continuous
B) batch
C) repetitive
D) job shop
E) subcontracting

F) B) and D)
G) A) and C)

Correct Answer

verifed

verified

"Balance delay" is another name for the percentage of idle time in a product layout.

A) True
B) False

Correct Answer

verifed

verified

The goal of line balancing is to assign tasks to workstations in such a way that the workstations have approximately equal time requirements.

A) True
B) False

Correct Answer

verifed

verified

As a general rule, continuous processing systems produce products for inventory rather than for customer order.

A) True
B) False

Correct Answer

verifed

verified

The type of layout in which workers, materials, and equipment are moved to the product as needed is:


A) process.
B) product.
C) fixed-position.
D) batch.
E) mass.

F) A) and B)
G) All of the above

Correct Answer

verifed

verified

A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $.50 per load meter moved. An analyst has prepared the following flow and distance matrices:  Distances (meters)   Flows (loads per week  From/To  I  II  III  I 1020 II 10 III  From/To XYZX080Y30150Z100130\begin{array}{l}\text { Distances (meters) } \quad\quad\quad\quad\quad\quad \text { Flows (loads per week }\\\begin{array}{rlll}\text { From/To } & \text { I } & \text { II } & \text { III } \\\hline \text { I } & - & 10 & 20 \\\text { II } & & - & 10 \\\text { III } & & & -\end{array}\quad\quad\begin{array}{rlll}\text { From/To } & \mathrm{X} & \mathrm{Y} & \mathrm{Z} \\\hline \mathrm{X} & - & 0 & 80 \\\mathrm{Y} & 30 & - & 150 \\\mathrm{Z} & 100 & 130 & -\end{array}\end{array} What are total weekly costs for an optimum layout?


A) $2,600
B) $3,600
C) $6,200
D) $7,200
E) $8,200

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

In cellular manufacturing, machines and equipment are grouped by type (e.g., all grinders are grouped into a cell).

A) True
B) False

Correct Answer

verifed

verified

Given the following line balance data:  Task  Predecessor  Time (seconds) t none 15ut14vt7wu6xv8yw,x10zy21\begin{array} { l c c } \text { Task } & \text { Predecessor } & \text { Time (seconds) } \\\hline \mathrm { t } & \text { none } & 15 \\\mathrm { u } & \mathrm { t } & 14 \\\mathrm { v } & \mathrm { t } & 7 \\\mathrm { w } & \mathrm { u } & 6 \\\mathrm { x } & \mathrm { v } & 8 \\\mathrm { y } & \mathrm { w } , \mathrm { x } & 10 \\\mathrm { z } & \mathrm { y } & 21\end{array} For eight hours of operating time per day and a desired output rate of 960 units per day, what is the minimum number of stations needed to achieve the appropriate cycle time?

Correct Answer

verifed

verified

Which of the following is not a characteristic of layout decisions in system design?


A) substantial investment of both money and effort
B) long-term commitment
C) significant impact on short-term efficiency
D) usually well received by operative personnel
E) can affect supplier or customer processes

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

Product layouts involve high utilization of labor and equipment.

A) True
B) False

Correct Answer

verifed

verified

Heuristic rules are used primarily in which of these types of layouts? (I) Product (II) Process (III) Fixed-position


A) I
B) II
C) I and III
D) I and II
E) II and III

F) D) and E)
G) A) and E)

Correct Answer

verifed

verified

Which of the following process types would be most likely to be used in the maturity phase of a product's life cycle?


A) repetitive
B) intermittent
C) project
D) batch
E) job shop

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved in the production of a Mint Chocolate Chip Cookie.  Task  Time ( secs )  Immediate Predecessor u4 none v14uw12 Vx12 Vy6wz8x,y\begin{array} { l l l } \text { Task } & \text { Time } ( \text { secs } ) & \text { Immediate Predecessor } \\\hline \mathrm { u } & 4 & \text { none } \\\mathrm { v } & 14 & \mathrm { u } \\\mathrm { w } & 12 & \mathrm {~V} \\\mathrm { x } & 12 & \mathrm {~V} \\\mathrm { y } & 6 & \mathrm { w } \\\mathrm { z } & 8 & \mathrm { x } , \mathrm { y }\end{array} For output to equal projected demand, what is the minimum number of workstations needed?


A) 6
B) 4.5
C) 3
D) 2.7
E) 2

F) C) and D)
G) A) and C)

Correct Answer

verifed

verified

Avoiding bottlenecks is the primary goal of product design.

A) True
B) False

Correct Answer

verifed

verified

QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product:  Task  Time (secs)   Immediate Predecessor  a 34 none  b 20 a  c 10 b  d 16 b  e 10 c  f 24 d, e  g 38 f \begin{array} { l l l } \text { Task } & \text { Time (secs) } & \text { Immediate Predecessor } \\\hline \text { a } & 34 & \text { none } \\\text { b } & 20 & \text { a } \\\text { c } & 10 & \text { b } \\\text { d } & 16 & \text { b } \\\text { e } & 10 & \text { c } \\\text { f } & 24 & \text { d, e } \\\text { g } & 38 & \text { f }\end{array} For output to equal forecasted demand, what is the minimum number of workstations needed?


A) 1
B) 3
C) 3.75
D) 4
E) 5

F) C) and D)
G) A) and D)

Correct Answer

verifed

verified

Showing 121 - 140 of 150

Related Exams

Show Answer