Filters
Question type

Study Flashcards

A flexible budget shows budgeted costs at several different levels of activity.

A) True
B) False

Correct Answer

verifed

verified

Costs that vary in some degree with the volume of activity, but not in direct proportion to it are called----------- costs.

Correct Answer

verifed

verified

semi-varia...

View Answer

Complete the flexible budget of manufacturing costs for Lansome Industries for September 2019. Overhead is based on direct labor hours. Lansome Industries Budget of Manufacturing Costs Month of September 2019  Complete the flexible budget of manufacturing costs for Lansome Industries for September 2019. Overhead is based on direct labor hours. Lansome Industries Budget of Manufacturing Costs Month of September 2019     \begin{array}{|c|l|l|r|} \hline \text { Depreciation } & (19) & \underline{1,750} & \underline{(20)} \\ \hline \text { Total fixed costs } & (21) & \underline{(22)} & \underline{6,235} \\ \hline \text { Total manufacturing overhead } & (23) & (24) & \underline{11,985} \\ \hline \end{array}  Depreciation (19)1,750‾(20)‾ Total fixed costs (21)(22)‾6,235‾ Total manufacturing overhead (23)(24)11,985‾\begin{array}{|c|l|l|r|}\hline \text { Depreciation } & (19) & \underline{1,750} & \underline{(20)} \\\hline \text { Total fixed costs } & (21) & \underline{(22)} & \underline{6,235} \\\hline \text { Total manufacturing overhead } & (23) & (24) & \underline{11,985} \\\hline\end{array}

Correct Answer

verifed

verified

Lansome Industries
B...

View Answer

Determine the cost behavior for each of the following items as Fixed (F), Variable (V), or Semi-variable (S). Production Level Determine the cost behavior for each of the following items as Fixed (F), Variable (V), or Semi-variable (S). Production Level

Correct Answer

verifed

verified

(1) F, (2) V, (3) V,...

View Answer

Match the following descriptions with the appropriate term.

Premises
The difference between the total standard cost and the total actual cost
The difference between the actual price and the standard cost for materials multiplied by the actual quantity of materials used
The difference between the actual hours worked and the standard labor hours allowed fo the job multiplied by the standard cost per hour
Shows the per unit standard costs for materials, labor, and overhead
Explains the difference between standard cost and actual cost
The difference between actual and standard overhead costs
The difference between the actual labor rate per hour and the standard labor rate per hou multiplied by the actual number of hours worked on the job
The difference between the actual quantity used and the quantity of materials allowed multiplied by the standard cost of the materials
Responses
Cost variance
Labor efficiency variance
Labor rate variance
Materials price variance
Materials quantity variance
Overhead variance
Standard cost card
Variance analysis

Correct Answer

The difference between the total standard cost and the total actual cost
The difference between the actual price and the standard cost for materials multiplied by the actual quantity of materials used
The difference between the actual hours worked and the standard labor hours allowed fo the job multiplied by the standard cost per hour
Shows the per unit standard costs for materials, labor, and overhead
Explains the difference between standard cost and actual cost
The difference between actual and standard overhead costs
The difference between the actual labor rate per hour and the standard labor rate per hou multiplied by the actual number of hours worked on the job
The difference between the actual quantity used and the quantity of materials allowed multiplied by the standard cost of the materials

The labor standard for a product was 5.5 hours at a wage rate of $9 per hour. The firm produced 1,020 units of the item. Labor costs totaled $50,414 and 5,540 hours of labor were used. An analysis of labor costs would indicate


A) a $554 favorable labor time variance.
B) a $554 unfavorable labor time variance.
C) a $630 unfavorable labor rate variance.
D) a $630 favorable labor rate variance.

E) A) and D)
F) C) and D)

Correct Answer

verifed

verified

Vista Company's records show the following information for the first six months of 2019. Vista Company's records show the following information for the first six months of 2019.     1. What are the variable costs per hour using the high-low point method? 2. What are the fixed costs per month using the high-low point method? 1. What are the variable costs per hour using the high-low point method? 2. What are the fixed costs per month using the high-low point method?

Correct Answer

verifed

verified

The company's accountant developed the data given below for Product X for the year 2019. Use this information to calculate the answers to the questions that follow. Total budgeted production: 10,000 units Raw materials: 5 units of raw materials, costing $1.75 per unit, required for each unit of finished goods Direct labor: 4 hours of labor at the rate of $12 per hour required for each unit of finished goods Mfg. overhead: $70,000 budgeted for 10,000 units of finished goods 1. What is the standard cost per unit of product for materials? 2. What is the standard cost per unit of product for labor? 3. What is the standard cost per unit of product for overhead? 4. What is the total standard cost per unit of product?

Correct Answer

verifed

verified

1. $8.75; ...

View Answer

A price variance for an item is the difference between its actual price and its standard price multiplied by the standard quantity.

A) True
B) False

Correct Answer

verifed

verified

The difference between the total standard cost and the total actual cost is the----------- .

Correct Answer

verifed

verified

Petersen Company produces a single product with the following production and average cost data: Petersen Company produces a single product with the following production and average cost data:   - The best estimate of total cost at an activity level of 7,250 units is: A) $424,500 B) $453,125 C) $505,125 D) $458,250 - The best estimate of total cost at an activity level of 7,250 units is:


A) $424,500
B) $453,125
C) $505,125
D) $458,250

E) None of the above
F) C) and D)

Correct Answer

verifed

verified

The purchasing department can determine the standard quantity per unit of each type of raw material required to manufacture a product.

A) True
B) False

Correct Answer

verifed

verified

In a factory, the fixed costs per unit are $60 when 500 units are produced. If 600 units are produced, the fixed costs per unit would be


A) $60.00.
B) $55.00.
C) $50.00.
D) $50.63.

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

Weaver Corporation has a three-year contract with a security firm that sets hourly wage rates for the firm at $10 per hour. At 7,000 units of output, factory security costs were $14,000. Production is expected to increase next year to a level of 10,000 units and the security costs are expected to remain the same. The security costs are an example of fixed factory costs.

A) True
B) False

Correct Answer

verifed

verified

Which of the following costs are generally semi-variable?


A) repairs and maintenance
B) depreciation
C) clerical salaries
D) property taxes

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

The price variance for an item is the difference between its actual price and its standard price, multiplied by the--------- quantity.

Correct Answer

verifed

verified

A budget that shows expected costs at more than one level of activity is called a(n)----------budget.

Correct Answer

verifed

verified

Which variance is controllable by the purchasing manager?


A) standard overhead variance.
B) labor rate variance.
C) material price variance.
D) material usage variance.

E) None of the above
F) C) and D)

Correct Answer

verifed

verified

The standard costs for a unit of product are shown below.  Materials: 2 pounds at $1.00 per pound $2.00 Labor: 1 hours at $10.00 per hour 10.00 Overhead: 60% of directlabor 6.00\begin{array} { l l r } \text { Materials: } & 2 \text { pounds at } \$ 1.00 \text { per pound } & \$ 2.00 \\\text { Labor: } & 1 \text { hours at } \$ 10.00 \text { per hour } & 10.00 \\\text { Overhead: } & 60 \% \text { of directlabor } & 6.00\end{array} During June, Job N-5 for 100 units was completed. The actual costs of the job are shown below.  Materials: 300 pounds at $1.45 per pound $435.00 Labor: 200 hours at $9.50 per hour 1,900 Overhead Applied: 60% of direct labor 1,140\begin{array}{llll}\text { Materials: } & 300 &\text { pounds at } \$ 1.45 \text { per pound } & \$ 435.00 \\\text { Labor: } & 200& \text { hours at } \$ 9.50 \text { per hour } & 1,900 \\\text { Overhead Applied: } & 60 \% &\text { of direct labor } & 1,140\end{array} 1. What is the total cost variance between actual cost and standard cost? 2. What is the total material variance? 3. What is the material quantity variance? 4. What is the material price variance?

Correct Answer

verifed

verified

1. $1,675.00 unfavor...

View Answer

Efficiency and cost control can be evaluated by comparing actual overhead costs with the budget for the actual level of operations with the


A) flexible budget.
B) fixed budget.
C) manufacturing cost budget.
D) budget performance report.

E) C) and D)
F) None of the above

Correct Answer

verifed

verified

Showing 21 - 40 of 126

Related Exams

Show Answer